10/5/2010
-Edited the population equivalent table, inserted the detailed break down of the new revised layout plan for area A05, A06 and A13.
-Calculated the water demand according to sections for low zone, sector B, Sri Damansara.
11/5/2010
-Finalized the population equivalent table.
-Current cumulative population equivalent is 81486. The cumulative population equivalent with the new revised layout plan is about 102455.
12/5/2010
-Went to 3 landfill sites, Sua Betong, Pajam and Bukit Palong.
-The HDPE was not fixed properly at the leachate pond in Pajam.
-The water stop which is used at every concrete casting stop was not fixed properly.
13/5/2010
-Checked the beams of housing project (Phase 3F), checked if the names and sizes in the drawings were accurate.
14/5/2010
-Went to site with Law Lok Hong, Emerald West Phase 3F development in Rawang. Attended the site meeting.
-Took photos of show house which was being constructed.
-First floor slabs completed, columns erected.